Project Details
Â
- Location: Guardsman Way, on the site of the former Utah Baseball practice field
- Ground Broken: Summer 2024
- Stadium Complete: Spring 2026
Timelines contingent upon construction schedules
Â
Ballpark Features
Â
- FieldTurf playing surface
- Permanent seating for 1,200 fans, plus grass berm seating in the outfield (bringing total capacity is 3,000)
- Baseball support spaces including locker rooms, coaches' offices, medical space, equipment storage, indoor batting/pitching cages and press box
- Fan amenities including concessions, restrooms, ticket office and merchandise
- Estimated project cost is $35 million, with the majority privately raised
Â
Renderings subject to change with evolution of project
Â
Project Progress
Â
August 2025 // Photo Gallery
The FieldTurf playing surface, dugout rails and backstop/wall padding have been installed, meaning the Utes officially can practice inside the facility later this month.
Netting, the foul poles and pitch clocks have also been installed and interior work is progressing as well.
Â
Gallery: (8-8-2025) Ballpark Construction Update (8/2025)
June 2025 // Photo Gallery
Installation of steel has completed in the main stadium structure, while steel and masonry work is ongoing at the adjacent indoor practice facility. On Level 1 of the main stadium, interior framing has begun. Out on the field, subgrade work has begun in preparation for turf installation and the batter's eye has been completed in center field.
Â
Gallery: (6-13-2025) Ballpark Construction Update (6/2025)
May 16, 2025: Topping Out Ceremony // Photo Gallery
Members of the Utah Baseball team visited Charlie Monfort Field at America First Ballpark to celebrate the final steel beam being raised and placed into the structure. The student-athletes, coaching and support staff, construction members and a few additional supporters were on hand to sign the beam. After it was secured, everyone in attendance enjoyed hot dogs near where the future pitcher's mound will be located.
Masonry work throughout the main ballpark structure has moved along at an impressive pace. In addition, concrete is being poured for the Utes' adjacent indoor facility.
Â
Gallery: (5-16-2025) BSB: Topping Out Ceremony (5/16/25)
March 2025 // Photo Gallery
Placement of structural steel has begun in the spaces that will become the home and visitor dugouts, as well as the basement areas. Masonry work is ongoing throughout the West stair tower and ticket office. In addition, foundations are being poured for the adjacent practice facility.
Gallery: (3-31-2025) Ballpark Construction Update (3/2025)
Â
February 2025 // Photo Gallery
Concrete foundations are being poured in structures near left field, while the waterproofing process has begun for foundations all through the ballpark. Plumbers have been on-site completing drainage work in what will become the Utah dugout, while electricians have completed underground conduits. Additional footings are also being excavated on site.
Gallery: (2-15-2025) Ballpark Construction Update (2/15/25)
December 2024 // Photo Gallery
Construction crew members are working on the home team dugout space, as well as making progress on concrete footings, walls and column piers throughout the ground level.
Gallery: (1-2-2025) Ballpark Construction Update (12/2024)
November 2024 // Photo Gallery
Concrete has begun pouring into footings along the West side of the ballpark, into what will eventually become the visiting team dugout. Footings are being dug elsewhere on site and utility work is progressing throughout the ballpark. Miscellaneous ground work and preparation is taking place for next stages in construction, including larger material being crushed down into finer material for backfill.
Â
Gallery: (11-7-2024) Ballpark Construction Update (11/7/24)
October 2024 // Photo Gallery
Construction crews are continuing work on the ballpark site; at this stage work is progressing on utility tie-ins and storm lines. In addition, crew members are digging for footings and preparing the footings for concrete pouring.
Â
Gallery: (10-3-2024) Ballpark Construction Update (10/3/24)
August 28, 2024: Construction Celebration // Event Recap + Quotes // Photo Gallery
Over 150 guests gathered for a construction celebration at the future site of Charlie Monfort Field at America First Ballpark. Once the main event program concluded, guests stuck around to enjoy hot dogs and light refreshments—all while looking ahead to a new era of Utah Baseball.
Â
Gallery: (8-28-2024) BSB: Construction Celebration (8/28/24)
Summer 2024: Ground Broken
Construction has begun on Charlie Monfort Field at America First Ballpark. Initial site preparation involved removing elements of the former Utah Baseball practice field, including the backstop, dugouts, outfield fence and scoreboard. The former indoor hitting building was demolished and the field surface was cleared.
Gallery: (8-14-2024) Ballpark Construction Update (8/14/24)
Many people have helped us in documenting the progress of ballpark construction. In no particular order, thanks to Gavin Gough, Jason Greco, Chris Nelson, Melody Murdock, Sophia Kuder, Davis Kuhn, Kaity Yarrow, Nathan Dutta, Cayden Parke, Justin Discoe, Chris Frkovich and others who have been of great assistance.